A construction estimate example, the way it should look

An estimate is more than a number, it is the roadmap for the whole job. Here is a real UK extension priced the way Builder Expert delivers every estimate: by phase, by task, ready for your client.

What is in it

Six things every estimate should give you

A good estimate wins the job, protects the margin and keeps the project on track. These are the parts that do the work.

A clear total cost

One headline figure, ex and inc VAT, so you and your client know the number from day one.

Phase-by-phase breakdown

Every stage priced on its own, from preliminaries to finishes, so nothing hides in a lump sum.

Built-in contingency

A costed allowance for the unknowns, so a surprise on site does not become a loss on paper.

Visual cost distribution

See at a glance where the money goes, phase by phase, before you commit to the job.

Itemised quantities and rates

Every task measured out with its own quantity and unit rate, so the price is transparent and easy to check.

Client-ready PDF

Your logo, your VAT number, an itemised document you can hand a client with confidence.

The worked example

Single-storey rear extension, priced phase by phase

Project summary

Single-storey rear extension · 5m × 5m · Surrey

Preliminaries
£6,092
Demolition
£2,440
Foundations and Footings
£10,868
Underground Drainage
£5,214
Structural Flooring
£6,587
Structural and Steelwork
£8,409
External Walls
£12,341
Roofing
£11,013
Joinery
£2,422
Plumbing and Heating
£6,838
Electrics
£5,782
Plastering
£3,557
Decorating
£1,672
Finishes
£2,789
Fitting Out
£5,234
Provisional Sums
£8,040
Total (inc VAT)£119,158.56

Payment schedule

Staged payments, tied to real milestones

Every estimate can carry a payment schedule, so cash flow follows progress on site instead of guesswork.

On start

Mobilisation

£11,916

Week 2

Foundations complete

£23,832

Week 5

Structure watertight

£35,748

Week 8

First fix complete

£23,832

Week 11

Second fix and finishes

£17,874

Week 12

Practical completion

£5,957

Bill of quantities

Every line, itemised by task

Under the totals sits the detail: each task, its quantity and its price. A sample of the full bill of quantities below.

PhaseTaskQtyPrice
PreliminariesSupply and install scaffolding (per storey of elevation)15 LM£1,710.00
PreliminariesDisconnect and make safe gas, water and electrical services2 Day£684.00
DemolitionDemolish external walls and clear the rubbish away15 M2£1,887.90
Foundations and FootingsExcavate and cast trench foundations, remove soil from site9 M3£6,215.94
Foundations and FootingsCast reinforced ground beams, including shuttering and beam formation5 LM£2,199.20
Underground DrainageExcavate and install 110mm underground drainage pipework14 LM£1,784.44

Illustrative sample. A full estimate itemises every phase of the job. All prices exclude VAT.

Want an estimate like this for your project?

Draft it yourself with BEX AI in minutes, or send us your drawings and we prepare it for you.

FAQ

Estimate example, answered

Is this a real estimate?

The figures shown are a real example from a UK single-storey rear extension. Your own estimate is priced against your drawings and specification, against live UK construction rates.

What does an estimate cost?

A Basic Estimate is a flat £90 and arrives the next working day. Detailed Estimates run £110 to £280 by project type. All prices exclude VAT.

Can I get one built for my project?

Yes. Send your drawings or project notes and our estimators prepare an itemised, branded PDF, or draft it yourself in minutes with BEX AI.