A mansard loft conversion in the UK typically costs £52,000 to £140,000 finished, supplied and installed including VAT, which works out at roughly £2,450 to £3,500 per m² of new floor area before any London uplift. It is the most expensive loft type because the rear roof slope is demolished and rebuilt, not altered. This page is for the builder pricing a mansard loft conversion, and for the client he is explaining the figure to.
All figures here are current UK market ranges for the finished job including VAT, the same throughout the page. They assume a properly run, tax paying firm with qualified trades at the middle to upper end of the normal market band: high against the cheapest crews, low against a high end London firm.
What a mansard loft conversion is
A mansard rebuilds one roof slope, almost always the rear, as a near vertical wall set at about 70 to 72 degrees from horizontal, with a flat or very shallow roof over the top. On a terrace it is usually built in masonry off the existing party walls, which are raised to take it, so the new room keeps close to full headroom right across the footprint rather than only under the ridge.

A double mansard does the same to the front slope as well. An L shaped mansard carries the new structure over the rear outrigger or side return, which is how London terraces gain a second bedroom and a bathroom in the loft.
Why a mansard is the most expensive loft type
A roof light conversion opens windows into the slope that is already there. A dormer takes out roughly half the rear slope and builds a box into it. A mansard takes the whole slope out and rebuilds it:
- The existing rear roof structure is demolished and rebuilt rather than altered, so the house is open to the weather and needs a temporary roof over the scaffold.
- The party walls are usually raised in blockwork or brickwork on both sides, which means work on the boundary and the notices that go with it.
- New floor beams and structural steel carry the new wall and floor loads down into the existing structure.
- The scaffold is bigger, stays up longer and usually needs a licence where it stands on the public highway.
- Planning permission is normally required, which adds months before anyone starts.
Those five points are the whole price gap. For how a mansard sits against the other loft types, see our loft conversion cost guide by type.
Mansard loft conversion cost by type
Finished, supplied and installed, including VAT: structure, roof covering, insulation, windows, staircase, one en-suite, plastering and decoration.
| Mansard type | Typical new floor area | Finished cost (supplied and installed, incl. VAT) |
|---|---|---|
| Single rear mansard, mid terrace | 20 to 25 m² | £52,000 to £85,000 |
| Full width mansard, mid terrace or end terrace | 25 to 35 m² | £65,000 to £115,000 |
| L shaped mansard over the side return or outrigger | 30 to 40 m² | £80,000 to £130,000 |
| Double mansard, front and rear | 30 to 40 m² | £85,000 to £140,000 |
Mansard cost by size
| New floor area | Finished cost (incl. VAT) | Cost per m² |
|---|---|---|
| 20 m² | £52,000 to £70,000 | £2,600 to £3,500 |
| 30 m² | £75,000 to £105,000 | £2,500 to £3,500 |
| 40 m² | £98,000 to £136,000 | £2,450 to £3,400 |
Mansards are concentrated in London and the South East, and prices there run 15 to 25% above these figures, so a 25 m² single rear mansard that is £60,000 to £85,000 in the Midlands is commonly £70,000 to £105,000 inside the M25.
What the price includes, in build order

Scaffold, temporary roof and protection through the house; strip out and demolition of the existing rear slope; new floor beams and structural steel on padstones; masonry or timber frame to the new near vertical walls and the raised party walls; flat roof covering, upstands, fascia and gutters; windows and any dormer windows in the new slope; the new staircase and the opening it needs; first fix plumbing and electrics; insulation to current Part L standards; plasterboard and skim; second fix, decoration and floor finishes; making good to the rooms below and the landing.
Preliminaries (scaffold, scaffold licence, skips, welfare, protection and parking) sit inside that total and typically run at 10 to 15% of it. They are not an extra bolted on at the end, and a quote that leaves them out is not cheaper, it is incomplete.
Fees, which are not part of the build price
These are paid to other people and sit outside the build cost above.
| Fee | Typical current UK range |
|---|---|
| Architect or designer, drawings and specification | £1,800 to £4,500 |
| Structural engineer, calculations and details | £800 to £2,000 |
| Householder planning application, England | £528 |
| Lawful development certificate, proposed work | £264 |
| Building control, full plans or building notice | £900 to £1,800 |
| Party wall surveyor, per adjoining owner | £1,000 to £2,000 |
The householder planning fee in England has been £528 since 1 April 2025, and the certificate of lawfulness for proposed work is half that at £264. The current schedule is published on the Planning Portal fee page.
Planning permission on a mansard
A mansard is rarely permitted development, because it changes the shape and the pitch of the roof and usually raises the party walls, so a full householder application is the normal route. Watch for:
- Conservation areas, where permitted development rights are already cut back.
- Article 4 directions, which remove roof alteration rights borough by borough.
- London borough design guides, several of which set out exactly what a mansard must look like (pitch, materials, window proportions, how it meets the parapet).
- Flats and maisonettes, which never have permitted development rights for roof alterations.
Allow 8 to 13 weeks for a decision on a householder application, longer where a design is negotiated.
Party wall work on a mansard
On a terrace the new structure is built off and above both party walls, so notices go to the adjoining owners on both sides under the Party Wall etc. Act 1996. Two months' notice is normal for party structure work. If a neighbour consents in writing there is no award and no surveyor; if they dissent or do not reply, an award is needed and the building owner pays the surveyor fees, typically £1,000 to £2,000 per adjoining owner, more in London or where each side appoints its own surveyor. Budget six to ten weeks for the party wall process before work starts, and read the government's party wall explanatory booklet for the notice procedure.
Fire safety: the Part B package

Every loft conversion, mansard included, needs a protected escape route down the stairs, FD30 doors to the habitable rooms off it, an escape window in the new room, mains wired interlinked alarms, and the floor below the loft upgraded to 60 minutes' fire resistance. On a typical two storey terrace going to three storeys that package is £3,000 to £6,000, and more where the whole stairwell has to be lined and every door changed.
The client's own budget
These are the lines the client sets, supplied and installed, and they move the total within the ranges above.
| Item | Typical budget range |
|---|---|
| Roof window, each | £700 to £1,600 |
| Dormer or sash window in the mansard face, each | £900 to £2,200 |
| En-suite sanitary ware and brassware | £1,200 to £4,500 |
| Flooring | £40 to £120 per m² |
| Fitted wardrobes | £1,500 to £6,000 |
| Staircase finish (balustrade, handrail, treads) | £2,500 to £7,000 |
How long a mansard takes
Design and planning take about three to four months before anyone is on site: two to four weeks for drawings and engineer's calculations, 8 to 13 weeks for the planning decision, with the party wall notices running alongside. On site, a single rear mansard is usually 10 to 14 weeks from scaffold to handover, and an L shaped or double mansard 14 to 20 weeks. The noisiest fortnight comes early.
What a cheap mansard quote has left out
The low end of any range is a specialist pricing a job he already understands on a straightforward terrace. A quote well below it is usually missing:
- The temporary roof and weatherproofing while the slope is off.
- The structural steel, padstones and the engineer's details that go with them.
- The Part B fire package, especially the 60 minute floor and the doors downstairs.
- Upgrading the existing staircase and landing so the escape route works.
- Making good and redecorating the rooms the new stair opening passes through.
- Party wall surveyor fees and the scaffold licence.
None of that is optional, so it comes back as extras, or as a rushed job, or as work done to the letter and not to the standard the client pictured.
Headroom: the mistake that is found too late
The usual loft problem is a client who has already decided on a dormer and only discovers at design stage that the ridge height leaves 1.9 m under the new ceiling once the floor is built up and the insulation is in. A mansard is often the answer precisely because it buys headroom a dormer cannot: the new wall goes up nearly vertical off the party walls, so the useful floor area is the whole footprint, not a strip down the middle. Measure from the top of the existing ceiling joists to the underside of the ridge before anyone promises a room.
Where the money actually goes
Clients picture the finished room: the oak floor, the wardrobes, the shower. On a mansard the bulk of the money is the part nobody sees, the demolition, the beams, the raised party walls, the new masonry and the flat roof deck. Finishes can be upgraded any time. The fundamentals cannot be touched again without ripping the finishes out, so they are funded first, and savings come from design and finishes, never from the structure.
Agreeing where the job ends
A mansard reaches into the rest of the house, so the line is written down before the scaffold arrives: whether the landing and the stairwell are redecorated, how far making good extends into the bedrooms below, who moves the loft tank and the aerial, what state the garden or the hallway is left in, and who pays for parking permits. Almost everything that later feels unpredictable sits in that grey area, and it is far easier to raise it now than halfway through.
Mansard loft conversion cost calculator
Mansard loft conversion cost estimator
- Finished build cost, incl. VAT
- £67,500
- Fees (design, engineer, planning, building control, party wall)
- £5,500
- Total including fees
- £73,000
Typical current UK market prices for a finished mansard conversion including VAT, with one en-suite included. Fees are a mid range allowance and rise where more than one adjoining owner appoints a surveyor.
Common questions
What is the cheapest type of loft conversion
A roof light or Velux conversion, at £25,000 to £45,000 finished and including VAT, because nothing structural changes outside the loft. It only works where the existing ridge already gives the headroom.
What are the disadvantages of a mansard roof
Cost, the planning risk, a flat roof that needs checking and recovering every 20 to 30 years, a longer scaffold period and more disruption inside the house than any other loft type.
What is the 10 year rule for loft work
In England, enforcement action against unauthorised building work must be taken within 10 years of substantial completion, for work finished on or after 25 April 2024. The old four year period only survives for work substantially completed before that date. It is not a shortcut: an unauthorised mansard is a problem on every sale until it is regularised.
Which parts of the job are the noisiest
The strip out of the old slope, cutting the party walls to take the new structure, and lifting and bolting the steel. That is the first week or two, and it is worth telling the neighbours before it starts rather than after.
Mansard, dormer or hip to gable
A dormer conversion of similar size runs about £45,000 to £75,000 finished, and a hip to gable with a rear dormer about £55,000 to £90,000, so a mansard costs roughly 25 to 40% more than a dormer on the same footprint. Where the existing roof gives reasonable headroom, a dormer reaches the same bedroom and bathroom brief for less money and less disruption. Our loft conversion cost guide by type sets out which roof suits which type.
Getting a price you can stand behind
A market range gives a budget. It does not price your roof, your party wall position, your access or your client's specification, and on a mansard those are most of the money.
See our detailed construction estimate service for a tender ready estimate on your own drawings, or check a price you already have against our guide to comparing builder quotes.
Last reviewed: November 2026.